NYC curb cut permits for a driveway, step by step

A new or wider curb cut for a driveway in New York City needs Department of Buildings approval: a licensed engineer or architect files plans in DOB NOW, DOB issues the permit only to a licensed General Contractor, and a separate DOT permit covers the work in the street. The job closes with inspections and a final survey.

What a curb cut is, legally

DOB defines a curb cut as a dip in the sidewalk with an angled cut in the curb, so a vehicle can drive from the street to a driveway, garage, parking area or loading dock. Because it changes the public sidewalk and curb, DOB treats it as an encroachment on the public right of way. A typical project has two parts:

  • The curb cut itself: the angled drop in the curb.
  • The driveway apron: the sloped section in the public right of way from the curb across the sidewalk to the parking area.

Behind it there is usually an off-street parking space, which the Zoning Resolution regulates too.

The steps, in order

  1. Hire a design professional. A New York State licensed Professional Engineer or Registered Architect prepares and submits the plans. Since 28 August 2017, curb cut filings must be made in DOB NOW: Build.
  2. Zoning analysis. The plans show the curb cut, driveway and parking space with the applicable Zoning Resolution sections. Zoning controls width and location: in many residential districts a curb cut must be at least 8 feet wide including splays, and districts set maximum widths and spacing between driveways.
  3. Drainage, if large enough. Where the proposed driveway and parking space exceed 200 square feet, the drawings include stormwater drainage details.
  4. DOB approval. DOB reviews the plans for safety and zoning compliance before issuing a work permit.
  5. Permits pulled by a licensed General Contractor. DOB issues curb cut permits only to a licensed General Contractor, who must also be registered in DOB’s online permit system.
  6. DOT permit. A separate permit from the Department of Transportation is required to install the curb cut, including any temporary sidewalk closure.
  7. Do the work to the approved drawings and DOT requirements, with New York 811 called before digging.
  8. Close the job. Inspections and sign-offs close the permit, including a final survey by a New York State licensed land surveyor.

Illegal curb cuts

DOB warns that illegal curb cuts typically carry multiple violations that must be corrected, and the costs add up quickly. Illegal curb cuts can be reported through 311. A city Comptroller audit has examined how DOB handles complaints about illegal curb cuts and driveways, so this is an area the city actively polices.

Before you start: three questions to ask

  1. Is there room under zoning? Lot width, front-yard rules and the distance to the next driveway decide whether a curb cut is possible at all. A design professional can answer this before you spend on drawings.
  2. What is in the way? Street trees, hydrants, light poles and bus stops near the proposed cut can block or complicate it.
  3. Where will the water go? A larger paved area means more runoff, and above 200 square feet DOB expects drainage details.

Where we fit in

We are a Home Improvement Contractor licensed by DCWP and registered as a General Contractor with the Department of Buildings. On a curb cut project, the design professional prepares and files the drawings. Once DOB approves them, we pull the DOB work permit and the DOT permit, build the curb cut, apron and driveway to the approved plans and DOT requirements, and support the inspections that close the job. See concrete driveways for how we build the driveway itself, and the driveway cost guide for budgeting.

This guide summarises official DOB and DOT material in plain English; the linked official pages govern, and your design professional confirms the requirements for your lot.

Need the work done? Concrete driveways — Across NYC, we break out old driveways and pour new concrete ones on a properly built base, with reinforcement, joints and a fall that sends water away from the house. Where the driveway crosses the public sidewalk, we build that section to the city's 7-inch standard.

Questions we get asked

Can I make a curb cut without a permit?

No. DOB states that no curb cut installation or construction can be done without a registered design professional submitting drawings and obtaining approval, and without a licensed contractor obtaining a DOT permit. Illegal curb cuts draw violations that must be corrected.

How wide can my curb cut be?

Zoning sets it. In many residential districts the minimum width of a curb cut is 8 feet including splays, and districts set maximum widths and spacing between driveways. Your engineer or architect checks the rules for your zoning lot.

Do I need drainage plans?

If the new driveway and parking space together exceed 200 square feet, DOB's guidelines call for stormwater drainage details in the drawings.

Who can pull the curb cut permit?

DOB issues curb cut permits only to a licensed General Contractor. Home Improvement Contractor licences are issued separately by DCWP.